36 workmen are emplyed to finish a certain work in 48 days.but its is found that in 24 days,only 2/5 work is done.how many more men must be taken to finish the work in time.
A. 16
B. 20
C. 18
D. none of these
Solution(By Examveda Team)
2/5 = (2*100)/5 = 40% work completed in 24 days.
See, 60% more is required to complete in 24 days.
If 36 worker works for rest 48 days then work will be 80% completed.
To complete 20% more work within the time they need 18 workers more.
Join The Discussion
Comments ( 1 )
Related User Ask Questions
Which of the following is not a primary function of a Bank?
A. Granting Loans
B. Collecting Cheques/Drafts customers
C. Facilitating import of goods
D. Issuing Bank Drafts
A. Regulatory jurisdictional fight between SEBI and IRDA
B. They don’t offer better tax benefits
C. They offer lesser returns compared to traditional insurance policies
D. All of the above
The Chameli Devi Jain Award is given for an outstanding woman ____?
A. Scientist
B. Reporter
C. Player
D. Teacher
24*36*.6=m2*24*.4, m2=54 and extra men needed is 54-36=18 ans