A, B and C can complete a piece of work in 24,6 and 12 days respectively.Working together, they will complete the same work in:

A. 1/24 days

B. 7/24 days

C. 24/7 days

D. 4 days


This Question Belongs to User Ask Question >> Miscellaneous

Join The Discussion

Comments ( 2 )

  1. Kumar Chandan
    Kumar Chandan :
    8 years ago

    Work Rate of A = 100/24 = 4.16% per day.
    Work Rate B = 100/6 = 16.66% per day.
    Work rate of C = 100/12 = 8.33% per day.
    Work Rate (A + B +C) = 4.16 + 16.66 + 8.33 = 29.15% per day.
    So, they can complete the work together in,
    100/29.15 = 3.43 days = 24/7 days.