A can do a piece of work in 10 days, B in 15 days. They work together for 5 days, the rest of the work is finished by C in two more days. If they get Rs. 3000 as wages for the whole work, what are the daily wages of A, B and C respectively (in Rs):

A. 200, 250, 300

B. 300, 200, 250

C. 200, 300, 400

D. None of these


This Question Belongs to User Ask Question >> Miscellaneous

Join The Discussion

Comments ( 1 )

  1. Kumar Chandan
    Kumar Chandan :
    8 years ago

    Work Rate of A = 100/10 = 10% per day.
    Work rate of B = 100/15 = 6.66% per day.
    Work Completed by A and B in 5 days = 5 * (10 + 6.66) = 83.33%.
    So, A completed = 5 *10 = 50% work, thus will get 50% of 3000 = 1500.
    Daily wage of A = 1500/5 = 300.
    B completed = 5 * 6..66 = 33.33% work.
    B get = 1000.
    Daily wage of = 200.
    C will get = 500.
    Daily wage of C = 250.