C is 20% more efficient than A. A &B can finish the work in 16 days. B &C can finish the work in 15 days. In how many days A alone can do the same piece of work?
A. 42
B. 48
C. 54
D. 36
Answer: Option B
Solution(By Examveda Team)
A and B can finish the work in 16 days.Work rate of,
(A + B) = 100/16 = 6.25% per day. ------------------- (1)
Work rate of,
B + C = 100/15 = 6.66% per day --------------------- (2)
Now,
C = A + 20% of A = 1.2 A ----------------------------------- (3)
Equations (1) - (2),
A + B - B - C = 6.25 - 6.66
A - C = - 0.41 ----------------------------------- (4)
Using equation (3),
A - 1.2 A = - 0.41
A = 2.05% per day.
So, A can complete the work in,
= 100/2.05 = 48 days (Approx.)
Fraction Method
Just Replace, 100% by 1.
A and B can finish the work in 16 days.
Work rate of,
(A + B) = 1/16 part per day. ------------------- (1)
Work rate of,
B + C = 1/15 part per day --------------------- (2)
Now,
C = A + 20% of A = 1.2 A ----------------------------------- (3)
Equations (1) - (2),
A + B - B - C = 1/16 - 1/15
A - C = -(1/240) ----------------------------------- (4)
Using equation (3),
A - 1.2 A = - (1/240)
.2A = 1/240
A = 1/(240*0.2) = 1/48 part per day
So, A can complete the work in,
= 48 days.
Join The Discussion
Comments ( 2 )
Which of the following is not a primary function of a Bank?
A. Granting Loans
B. Collecting Cheques/Drafts customers
C. Facilitating import of goods
D. Issuing Bank Drafts
A. Regulatory jurisdictional fight between SEBI and IRDA
B. They don’t offer better tax benefits
C. They offer lesser returns compared to traditional insurance policies
D. All of the above
The Chameli Devi Jain Award is given for an outstanding woman ____?
A. Scientist
B. Reporter
C. Player
D. Teacher
@Parasaran c is 20% more efficient
20% is 1/5 is fraction 20/100
So A is 5 and c is 6 i.e (5+1)
Now A+B= 16
And B+C= 15
If two take lcm of 16 and 15 which is 240 and that is your total work
Now efficiency of A is 5
Time taken by A is 240/5 = 48
Please explain without percentages plz.....