If 3 men or 4 women can construct a tower in 43 days, then how many days will 7 men and 5 women together take to construct it?
A. 14 days
B. 15 days
C. 13 days
D. 12 days
Solution(By Examveda Team)
4 women = 3 men1 women = 3/4 men.
5 women = (3 *5)/4 = 15/4 men.
7 men + 5 women = 7 + 15/4 = 43/4 men.
Now,
3 men can complete the work in 43 days.
1 men can complete it in = 43*3
43/4 men can complete = (43*3)/(43 /4) = (43 * 3 *4)/43 = 12 days.
Join The Discussion
Comments ( 1 )
Related User Ask Questions
Which of the following is not a primary function of a Bank?
A. Granting Loans
B. Collecting Cheques/Drafts customers
C. Facilitating import of goods
D. Issuing Bank Drafts
A. Regulatory jurisdictional fight between SEBI and IRDA
B. They don’t offer better tax benefits
C. They offer lesser returns compared to traditional insurance policies
D. All of the above
The Chameli Devi Jain Award is given for an outstanding woman ____?
A. Scientist
B. Reporter
C. Player
D. Teacher
Answer = D ( 12 days )