If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be :

A. 5 days

B. 4 days

C. 6 days

D. 7 days

Answer: Option B

Solution(By Examveda Team)

Let 1 man's 1 day's work = x and 1 boy's 1 day's work = y.
Then, 6x + 8y = 1/10  and 26x + 48y = 1/2,.
Solving these two equations, we get : x = 1/100 and y = 1/200 .
(15 men + 20 boy)'s 1 day's work = (15/100 + 20/200) = 1/4
So,  15 men and 20 boys can do the work in 4 days.


This Question Belongs to User Ask Question >> Miscellaneous

Join The Discussion

Comments ( 4 )

  1. Narendra B
    Narendra B :
    3 years ago

    Ans is 4

  2. Nitai Sarkar
    Nitai Sarkar :
    3 years ago

    1st condition = 10(6m+8b) here m= men & b= boys
    2nd condition = 2(26m+48b)
    3rd condition = X(15m+20b) here X= required time
    Since the all conditions are same.
    We get from 1st & 2nd conditions,
    60m+80b = 52m + 96b
    Or, 8m = 16b
    Or, m = 2b
    Now from 1st & 3rd conditions,
    (60×2b)+80b = X(15×2b+20b)
    Or, 200b = X (50b)
    Or, X = 200b/50b
    Or, X = 4 days

  3. Dakshin
    Dakshin :
    8 years ago

    b) 4 days

  4. Bhavin
    Bhavin :
    8 years ago

    give me a more easy method... its to long..