Examveda
Examveda

If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?

A. 60

B. 45

C. 40

D. 30

Answer: Option A

Solution(By Examveda Team)

1st method:
A and B complete a work in = 15 days
One day's work of (A + B) = $$\frac{1}{{15}}$$
B complete the work in = 20 days;
One day's work of B = $$\frac{1}{{20}}$$
Then, A's one day's work
$$\eqalign{ & = \frac{1}{{15}} - \frac{1}{{20}} \cr & = \frac{{4 - 3}}{6} \cr & = \frac{1}{{60}} \cr} $$
Thus, A can complete the work in = 60 days.

2nd method:
(A + B)'s one day's % work = $$\frac{{100}}{{15}}$$ = 6.66%
B's one day's % work = $$\frac{{100}}{{20}}$$ = 5%
A's one day's % work = 6.66 - 5 = 1.66%
Thus, A need = $$\frac{{100}}{{1.66}}$$ = 60 days to complete the work.

This Question Belongs to Arithmetic Ability >> Time And Work

Join The Discussion

Comments ( 4 )

  1. Mahesh
    Mahesh :
    1 year ago

    1/15-1/20
    Hw to solve

  2. Sivaprasath A.k
    Sivaprasath A.k :
    2 years ago

    If given A+B=15 days
    B=20 days
    A=?
    Sol:
    Formula use xy/x-y
    =15*20/15-20
    =300/5
    =60 so simple 😊

  3. DHANJIT MEDHI
    DHANJIT MEDHI :
    5 years ago

    A+B =15
    B= 20
    Taking lcm we get 60 dividing 60 by 15&20 we get values 4 and 3.
    4-3=1
    A`s 1 day work =1
    60 days work =60/1 = 60 days

  4. Gayathri Subramanian
    Gayathri Subramanian :
    9 years ago

    why should we do in a fraction?? n what is that 1 day?

Related Questions on Time and Work