'A' can do some work in 24 days 'B' can do it in 32 days and 'C' can do it in 60 days. They started working together, 'A' left after 6 days and 'B' left after working for 8 days, how Many more days are required to complete the work.

A. 30 days

B. 25 days

C. 22 days

D. 20 days


This Question Belongs to User Ask Question >> Miscellaneous

Join The Discussion

Comments ( 2 )

  1. Prithika Batra
    Prithika Batra :
    6 years ago

    Can it b solved by percentage method

  2. Sudhakar Prajapati
    Sudhakar Prajapati :
    8 years ago

    Correct Answer = 22 days
    -------------------------------------------
    Explanation :
    Work done by A in 1 day = 1/24
    Work done by B in 1 day = 1/32
    Work done by C in 1 day = 1/60

    Work done by A, B and C together in 1 day = 1/24 + 1/32 + 1/60 = 43/480
    After 6 days, A leaves.
    So, work done by A, B and C together in 6 days = 43/80

    Now, B and C work together for the next two days before B leaves.
    Work done by B and C together in 1 day = 1/32 + 1/60 = 23/480

    So, work done by B and C together in 2 days = 46/480 = 23/240

    Work remaining after A and B leaves = 1 - (43/80 + 23/240) = 1 - 152/240 = 88/240 = 11/30

    So 11/30 of the work is remaining for C to do alone.

    C completes 1 work in 60 days

    So, C completes 11/30 of the work in 11/30 * 60 days = 22 days