If flexible budget variance is $95000 and an actual cost is $40000, then flexible budget cost would be

A. $135,000

B. $45,000

C. $50,000

D. $55,000

Answer: Option D

Solution(By Examveda Team)

Flexible budget cost = Flexible budget variance - An actual cost
= $95000 - $40000 = $55,000.