31. The plinth area of a building not includes A. Area of the walls at the floor level B. Internal shaft for sanitary installations up to 2 sq m. in area C. Lift and wall including landing D. Area of cantilevered porch Answer & Solution Discuss in Board Save for Later Answer & Solution Answer: Option D No explanation is given for this question Let's Discuss on Board
32. In the mid-section formula A. The mean depth is the average of depths of two consecutive sections B. The area of mid-sections is calculated by using mean depth C. The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections D. All of the above Answer & Solution Discuss in Board Save for Later Answer & Solution Answer: Option D No explanation is given for this question Let's Discuss on Board
33. The inspection pit or chamber is a manhole provided in a base drainage system A. At every change of direction B. At every change of gradient C. At every 30 m intervals D. All the above Answer & Solution Discuss in Board Save for Later Answer & Solution Answer: Option D No explanation is given for this question Let's Discuss on Board
34. The cross-sectional area of the embankment of a canal fully in embankment in the given figure is A. $$\frac{1}{2}\left( {{{\text{b}}_1} + {{\text{b}}_2}} \right){\text{h}}$$ B. $$\left( {{{\text{b}}_1} + {{\text{b}}_2}} \right){\text{h}} + {\text{s}}{{\text{h}}^2}$$ C. $$\left( {{{\text{b}}_1} + {{\text{b}}_2}} \right) + 2{\text{s}}{{\text{h}}^2}$$ D. $$2\left[ {\left( {{{\text{b}}_1} + {{\text{b}}_2}} \right)\left( {{\text{b}} + {\text{s}}{{\text{h}}^2}} \right)} \right]$$ Answer & Solution Discuss in Board Save for Later Answer & Solution Answer: Option C No explanation is given for this question Let's Discuss on Board
35. Anti-siphonage pipe is connected to A. Main soil pipe B. Bottom of P trap W.C. C. Top of P trap W.C. D. Side of water closet Answer & Solution Discuss in Board Save for Later Answer & Solution Answer: Option C No explanation is given for this question Let's Discuss on Board
36. The 'centre line method' is specially adopted for estimating A. Circular buildings B. Hexagonal buildings C. Octagonal buildings D. All the above Answer & Solution Discuss in Board Save for Later Answer & Solution Answer: Option D No explanation is given for this question Let's Discuss on Board
37. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and A. Breadth of the wall B. Half breadth of wall on each side C. One fourth breadth of wall on each side D. None of these Answer & Solution Discuss in Board Save for Later Answer & Solution Answer: Option B No explanation is given for this question Let's Discuss on Board
38. According to ISI method of measurement, the order of the sequence is A. Length, breadth, height B. Breadth, length, height C. Height, length, breadth D. None of these Answer & Solution Discuss in Board Save for Later Answer & Solution Answer: Option A No explanation is given for this question Let's Discuss on Board
39. The rate of an item of work depends on A. Specifications of works B. Specifications of materials C. Proportion of mortar D. All the above Answer & Solution Discuss in Board Save for Later Answer & Solution Answer: Option D No explanation is given for this question Let's Discuss on Board
40. The cross-sections for a highway is taken at A. Right angle to the centre line B. 30 meters apart C. Intermediate points having abrupt change in gradient D. All the above Answer & Solution Discuss in Board Save for Later Answer & Solution Answer: Option D No explanation is given for this question Let's Discuss on Board