11.
The uplift pressure on a dam can be controlled by
i) constructing cutoff under upstream face
ii) constructing drainage channels bet-ween the dam and its foundation
iii) by pressure grouting in foundation
The corret answer is

12.
If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be

13.
The width of a meander belt is the transverse distance between

14.
Pick up the correct statement from the following:

18.
The amount of irrigation water required to meet the evapotranspiration needs of the crop during its full growth is called

20.
The intensity of irrigation means