41. For transferring the tunnel alignment through shafts, we adopt the following steps:
1.Hanging two or more plumb lines in the shaft
2.Determining the bearing of the plumb lines i.e. plumb plane
3.Suspending a 35 kg weight by each plumb line
4.Immersing the weights of both the plumb lines in the buckets containing water
The correct sequence of steps is:
1.Hanging two or more plumb lines in the shaft
2.Determining the bearing of the plumb lines i.e. plumb plane
3.Suspending a 35 kg weight by each plumb line
4.Immersing the weights of both the plumb lines in the buckets containing water
The correct sequence of steps is: