72.
Which of the following occurs when everyone involved in sourcing, producing and delivering the company's product works with the same information?

74.
Product layout is used when

77.
Which one of the following is not correct matching between level of facility planning and type of activity?

78.
Consider the following statements.
1. In PERT, it is assumed that the activity times follow the beta distribution.
2. In CPM, two time and cost estimates are made for each activity, which are called the optimistic and pessimistic estimates.
3. Time is the only variable used in PERT.
4. While in PERT the emphasise is on event, in CPM the emphasise is on activity.

79.
Match the following.
List-I List-II
a. Scheduling 1. Order
b. Sequencing 2. Control
c. Loading 3. What
d. Monitoring 4. When