Factory overhead can be charged on the basis of _______.

A. material cost

B. labour cost

C. prime cost

D. direct expenses

Answer: Option C

Solution(By Examveda Team)

Factory overhead can be charged on the basis of prime cost.

In costing, prime cost is the sum of direct materials cost, direct labor cost, and direct expenses involved in the production process. Therefore, factory overhead can be allocated based on the prime cost, which represents the direct costs associated with production.

Therefore, the correct answer is Option C: prime cost.

This Question Belongs to Commerce >> Costing

Join The Discussion

Comments ( 5 )

  1. Ishaan Kukkar
    Ishaan Kukkar :
    3 weeks ago

    Please confirm it.Why not b

  2. Vishwanath Bile
    Vishwanath Bile :
    3 years ago

    A

  3. Naresh Merugu
    Naresh Merugu :
    6 years ago

    ANS: All of the above

  4. Kanakaraju Perni
    Kanakaraju Perni :
    6 years ago

    C

  5. Aditi Dhana
    Aditi Dhana :
    6 years ago

    option D is correct

Related Questions on Costing