Examveda
Examveda

12 men and 18 boys, working $$7\frac{1}{2}$$ hours a day, can do a piece of work in 60 days. If a man works equal to 2 boys, then how many boys will be required to help 21 men to do twice the work in 50 days, working 9 hours a day ?

A. 30

B. 42

C. 48

D. 90

Answer: Option B

Solution(By Examveda Team)

1 man ≡ 2 boys ⇔ (12 men + 18 boys)
          ≡ (12 × 2 ×18) boys = 42 boys
Let required number of boys = x
⇒ (21 men + x boys) ≡ (21 × 2 × x) boys = (42 + x) boys
Less days, More boys (Indirect proportion)
More hours per day, Less boys (Indirect proportion)
More work, More boys (Direct proportion)
\[\left. \begin{gathered} \,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,{\text{Days 50}}:60 \hfill \\ {\text{Hours per day 9}}:\frac{{15}}{2} \hfill \\ \,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,{\text{Work }}1:2 \hfill \\ \end{gathered} \right\}::42:\left( {42 + x} \right)\]
$$\therefore \left[ {50 \times 9 \times 1 \times \left( {42 + x} \right)} \right] = $$     $$\left( {60 \times \frac{{15}}{2} \times 2 \times 42} \right)$$
$$\eqalign{ & \Leftrightarrow \left( {42 + x} \right) = \frac{{37800}}{{450}} \cr & \Leftrightarrow 42 + x = 84 \cr & \Leftrightarrow x = 42 \cr} $$

This Question Belongs to Arithmetic Ability >> Chain Rule

Join The Discussion

Related Questions on Chain Rule