2 men and 5 women can do 1/4th of a job in 3 days. After 3 days,1 man joined team and they completed another 1/4th of the job in 2 days. How many men can complete the job in 4 days?

A. 6

B. 24

C. 34

D. 12

Solution (By Examveda Team)

Work Rate of Man and Women,
(2/m) + (5/w) = 1/(4*3) ------------------------- (1)

(3/m) + (5/w) = 1/(4*2) -------------------------- (2)

(2) - (1),

1/m = 1/24

m = 24.
It means one man needs 24 days to complete the work so work to be completed in 4 days, we need

24/4 = 6 men.

 


This Question Belongs to User Ask Question >> Miscellaneous

Join The Discussion

Comments (2)

  1. Shakila Siddiquea
    Shakila Siddiquea:
    10 years ago

    6

  2. Leelanand Kumar
    Leelanand Kumar:
    10 years ago

    6 Men are needed to complete the job...