A 15 m3 dragline is deployed in an O.B. bench of an O.C. mine. It works for 40 days at the rate of 6 hrs per shift and 3 shifts a day. The cycle time, bucket fill factor, and operating efficiency of the dragline are respectively 50 s, 0.8, and 75%. The total volume of O.B. in m3 handled by the dragline is

A. 356918

B. 365918

C. 532158

D. 466560

Answer: Option D