A company is developing an advance version of their current software available in the market, what model approach would they prefer ?
A. RAD
B. Iterative Enhancement
C. Both RAD & Iterative Enhancement
D. Spiral
Answer: Option C
Related Questions on Software Engineering
Which of the following is not a phase of the Software Development Life Cycle (SDLC)?
A. Planning
B. Analysis
C. Testing
D. Maintenance
What does UML stand for in software engineering?
A. Unified Modeling Language
B. Universal Modeling Language
C. Unique Modeling Language
D. Unified Management Language
Which software development model is also known as the linear-sequential life cycle model?
A. Agile
B. Waterfall
C. Spiral
D. RAD (Rapid Application Development)
In which phase of the SDLC is the feasibility study conducted?
A. Planning
B. Design
C. Implementation
D. Maintenance