A concentrator pilot plant is fed with 1 tonne of copper ore at ROM grade of 1.5 % Cu. Metal recovery in the concentrator pilot plant is 90% and the grade of copper in concentrate is 20%. The amount of concentrate produced from 1 tonne of ore in kg is
A. 75.0
B. 72.0
C. 70.0
D. 67.5
Answer: Option D