A contract is to be complete in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, $$\frac{4}{7}{\text{ }}$$ of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?

A. 80

B. 81

C. 82

D. 83

Answer: Option B

Solution(By Examveda Team)

Remaining work
= $$\left( {1 - \frac{4}{7}} \right){\text{ = }}\frac{3}{7}$$
Remaining period = (46 - 33) = 13 days
Let the total men working at it be x
Less work, Less men (Direct proportion)
Less days, More men (Indirect proportion)
More hour/day, Less men (Indirect proportion)
\[\left. \begin{gathered} \,\,\,\,\,{\text{Work }}\frac{4}{7}:\frac{3}{7} \hfill \\ \,\,\,\,\,\,\,{\text{Men 13}}:33 \hfill \\ {\text{Hour/day }}9:8 \hfill \\ \end{gathered} \right\}::117:x\]
$$\eqalign{ & \therefore {\text{ }}\frac{4}{7} \times 13 \times 9 \times x = \frac{3}{7} \times 33 \times 8 \times 117 \cr & \Leftrightarrow x = \frac{{\left( {3 \times 33 \times 8 \times 117} \right)}}{{\left( {4 \times 13 \times 9} \right)}} \cr & \Leftrightarrow x = 198 \cr} $$
∴ Addition men to be employed = (198 - 117) = 81

This Question Belongs to Arithmetic Ability >> Chain Rule

Join The Discussion

Comments ( 2 )

  1. Beauty Of
    Beauty Of :
    3 years ago

    1-4/7=3/7 remaning work
    117*33*8/4/7=13*9(117+x)/3/7
    x=81

  2. Pragaya Upadhyay
    Pragaya Upadhyay :
    4 years ago

    in the above question 3/7 is the work remaining but its has been taken as work completed why??