A job is budgeted to require 3,300 productive hours after incurring 25% idle time. If the total labour cost budgeted for the job is Rs 36,300. What is the labour cost per hour( to the nearest cent)?
A. Rs 8.25
B. Rs 8.80
C. Rs 11.00
D. Rs 14.67
Answer: Option A
Join The Discussion
Comments ( 2 )
Related Questions on Costing
Basic objective of cost accounting is ________
A. tax compliance.
B. financial audit.
C. cost ascertainment.
D. profit analysis.
Process costing is suitable for ________.
A. hospitals
B. oil refing firms
C. transport firms
D. brick laying firms
The cost which is to be incurred even when a business unit is closed is a _____.
A. imputed cost
B. historical cost
C. sunk cost
D. shutdown cost
3300*100/75=4400
36300/4400=8.25
please post the solution