A job is budgeted to require 3,300 productive hours after incurring 25% idle time. If the total labour cost budgeted for the job is Rs 36,300. What is the labour cost per hour( to the nearest cent)?
A. Rs 8.25
B. Rs 8.80
C. Rs 11.00
D. Rs 14.67
Answer: Option A
3300*100/75=4400
36300/4400=8.25