A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?

A. 1.0 hour per unit

B. 1.2 hours per unit

C. 1.4 hours per unit

D. 1.6 hours per unit

Answer: Option A


This Question Belongs to Civil Engineering >> Engineering Economics

Join The Discussion

Comments ( 3 )

  1. Jayson Pereda
    Jayson Pereda :
    3 years ago

    An existing machine in a factory has an annual maintenance cost of P40,000. A new and more efficient machine will require an investment of P90,000 and is estimated to have salvage value of P30,000 at the end of 8 years. Its annual expenses for maintenance and upkeep, etc. Total P 22,000. If the company expects to earn 12% on its investment, will it be feasible to purchase the new machine using the present worth method

  2. Pragati Gadge
    Pragati Gadge :
    3 years ago

    Max production time per unit= ( per day demand/ operation time per day)
    = ( 7/7)= 1 hr per unit

  3. Pragati Gadge
    Pragati Gadge :
    3 years ago

    🍥Per day demand of generators= ( weekly demand)/ ( working days per week)
    =( 35/5) = 7 generators per day.