A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
A. 0.50
B. 0.66
C. 0.84
D. 0.95
Answer: Option C
Solution(By Examveda Team)
Standard deviation = square root of (variance) = square root of (1 * 1 + 2 * 2 + 2 * 2) = square root of (9) = 3D = 20
S = 3 + 8 + 6 = 17
Probability $$ = \frac{{\left( {{\text{D}} - {\text{S}}} \right)}}{{{\text{standard deviation}}}} = 1$$
Now, from Z table probability = 0.84.
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Join The Discussion