A push through system, according to which goods are manufactured for finished inventory solely, on basis of forecasted demand can be classified as
A. in-time production
B. materials requirement planning
C. on-time production
D. pull strategy of production
Answer: Option B
Solution (By Examveda Team)
A push through system, according to which goods are manufactured for finished inventory solely, on basis of forecasted demand can be classified as materials requirement planning. Material requirements planning (MRP) is a system for calculating the materials and components needed to manufacture a product.