A surface mine blast design has 9 holes in a row, each of 8 m length and 200 mm diameter. The spacing and burden are 6 m and 5 m respectively. The length of subgrade drilling is 1 m and the density of in-situ rock is 2.43 t/m3. Assuming no back break, the output per blast in t is
A. 4593
B. 5905
C. 6124
D. 6299
Answer: Option A