A unit cost calculated in costing system, by assigning total costs incurred to many similar units is categorized as

A. accounting period costing system

B. process costing system

C. job costing system

D. none of above

Answer: Option B

Solution(By Examveda Team)

A unit cost calculated in costing system, by assigning total costs incurred to many similar units is categorized as process costing system. Process costing is a type of operation costing which is used to ascertain the cost of a product at each process or stage of manufacture.

This Question Belongs to Commerce >> Costing