ABC analysis deals with
A. Analysis of process chart
B. Flow of material
C. Ordering schedule of job
D. Controlling inventory costs money
Answer: Option D
A. Analysis of process chart
B. Flow of material
C. Ordering schedule of job
D. Controlling inventory costs money
Answer: Option D
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion