Actual performance of a task is called
A. An event
B. An activity
C. A duration
D. None of these
Answer: Option A
Solution(By Examveda Team)
In the context of industrial engineering and production management, the actual performance of a task is referred to as an "event." An event represents a specific occurrence or action related to the task or process being monitored or analyzed. It is a significant happening within the context of the task's execution.The other options do not accurately describe the actual performance of a task:
Option B: An activity typically refers to a broader set of tasks or actions and may include multiple events.
Option C: A duration refers to the amount of time it takes to complete a task but does not capture the specific performance itself.
Option D: None of these is incorrect as "event" is the appropriate term for the actual performance of a task.
So, the correct answer is Option A: An event, which best represents the actual performance of a task in this context.
Join The Discussion
Comments ( 3 )
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Correct answer is B