Calculate the prime cost from the following information:
Direct material purchased: Rs. 1,00,000
Direct material consumed: Rs. 90,000
Direct labour: Rs. 60,000
Direct expenses: Rs. 20,000
Manufacturing overheads: Rs. 30,000

A. Rs. 1,80,000

B. Rs. 2,00,000

C. Rs. 1,70,000

D. Rs. 2,10,000

Answer: Option C