Consider the following number of activities with their start and finish time given below. Which of following activity will be left out?
| Activity | Starting time | Finish time |
| A1 | 1 | 2 |
| A2 | 3 | 5 |
| A3 | 4 | 6 |
| A4 | 5 | 8 |
A. A1
B. A2
C. A3
D. A4
Answer: Option C