CPM requires
A. Single time estimate
B. Double time estimate
C. Triple time estimate
D. None of these
Answer: Option A
Solution (By Examveda Team)
Correct Answer: A: Single time estimateLet's break down why!
CPM stands for Critical Path Method.
It's a project management technique.
CPM focuses on activities with a fixed, known duration.
Think of it like this: you know exactly how long each task will take.
Therefore, CPM only needs a single time estimate for each activity.
Options B and C (Double and Triple time estimate) are related to PERT, another project management technique.
PERT deals with uncertainty and uses multiple time estimates.
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion