Critical Path Net Work helps an engineer
A. To concentrate his attention on critical activities
B. To divert the resources from noncritical advanced activities to critical activities
C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. All of the above
Answer: Option D
Solution(By Examveda Team)
Critical Path Net Work helps an engineer- To concentrate his attention on critical activities
- To divert the resources from noncritical advanced activities to critical activities
- To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Join The Discussion