Crown pillar is at . . . . . . . .
A. Top of stope
B. Side of stope
C. Bottom of stope
D. Above drawing cross cuts
Answer: Option A
A. Top of stope
B. Side of stope
C. Bottom of stope
D. Above drawing cross cuts
Answer: Option A
A. Chip sampling
B. Channel
C. Bulk
D. Radio metre
The ore loaded in shrinkage stoping by . . . . . . . .
A. Over head mucker
B. Pneumatic Auto Loader
C. LHD
D. None
If the ore body is thicker, the level interval will be . . . . . . . .
A. More
B. Lessor
C. Stronger
D. Weaker
Join The Discussion