Directions (1 - 3): The following pie-chart shows the sources of funds to be collected by the National Highways Authority of India (NHAI) for its phase II projects. Study the pie-chart and answer the following three questions:
1.
If the toll is to be collected through and outsourced agency by allowing a maximum 10% commission how much amount should be permitted to be collected by the outsourced agency, so that the project is supported with Rs. 4,910 crores?
If NHAI could receive a total of Rs. 9,695 crores as External Assistance, by what percent (approximately) should it increase the market Borrowing to arrange for the shortage of funds?