During the Boston Big Dig project, how were groundwater challenges managed?

A. Freezing techniques

B. Pressurized grout curtains

C. Cement stabilization

D. Electro-osmosis

Answer: Option B

Solution (By Examveda Team)

Groundwater was controlled by constructing grout curtains around excavations, minimizing seepage into deep cut-and-cover tunnels.