Ensuring that no more than the allocated number of people are allocated at any given time in Software Scheduling is known as
A. Time Allocation
B. Effort Validation
C. Defined Milestone
D. Effort Distribution
Answer: Option B
A. Time Allocation
B. Effort Validation
C. Defined Milestone
D. Effort Distribution
Answer: Option B
Which of the following is not a phase of the Software Development Life Cycle (SDLC)?
A. Planning
B. Analysis
C. Testing
D. Maintenance
What does UML stand for in software engineering?
A. Unified Modeling Language
B. Universal Modeling Language
C. Unique Modeling Language
D. Unified Management Language
Which software development model is also known as the linear-sequential life cycle model?
A. Agile
B. Waterfall
C. Spiral
D. RAD (Rapid Application Development)
In which phase of the SDLC is the feasibility study conducted?
A. Planning
B. Design
C. Implementation
D. Maintenance