Factory overhead is Rs 3,00,000 and direct material cost is Rs 5,00,000 What is the overhead rate under direct material cost method?
Answer & Solution
Correct Answer:
Option
C
Overhead rate = Factory overhead / Direct material cost * 100
= 300000 / 500000 * 100 = 60%.
= 300000 / 500000 * 100 = 60%.