Factory overhead is Rs 3,00,000 and direct material cost is Rs 5,00,000 What is the overhead rate under direct material cost method?

Answer & Solution
Correct Answer: Option C
Overhead rate = Factory overhead / Direct material cost * 100
= 300000 / 500000 * 100 = 60%.
Examveda
Question posted by Examveda
Community

Join the Discussion

1 Comment
Naaresh Kumar
Naaresh Kumar 8 years ago
300000/50000*100=60%