Fixed position layout is also known as
A. Analytical layout
B. Synthetic layout
C. Static product layout
D. None of these
Answer: Option C
Solution(By Examveda Team)
Fixed position layout is also known as Static product layoutfixed position layout, personnel, supplies, and equipment are brought to the site where the product will be assembled, rather than the product being moved through an assembly line or set of assembly stations.
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion