For initial surveys of tunnels, the following activities are involved:
1.Marking portal point with concrete pillars on the ground
2.Marking tunnel obligatory points on the topographical maps
3.Preliminary setting of the tunnel on the topographical Survey of India maps
4.Driving lines between the fixed obligatory points
The correct sequence of the activities is:
A. 3, 2, 4, 1
B. 1, 2, 3, 4
C. 4, 3, 1, 2
D. 2, 4, 3, 1
Answer: Option A
Related Questions on Tunnel Engineering
A. (i) and (ii) are correct
B. (iii) and (iv) are correct
C. (i) and (iv) are correct
D. (ii) and (iii) are correct
Which of the following lining material is useful for shield driven tunnels in sub aqueous regions?
A. Stone masonry
B. Timber
C. Cast iron
D. Cement concrete
Which of the following methods of tunneling is used for long tunnels at great depths?
A. Army method
B. Needle beam method
C. Austrian method
D. English method
A. Only up holes
B. Only down holes
C. Horizontal or up holes
D. Horizontal down or up holes
Join The Discussion