For laying a sewer line in a trench of 2 m width, an offset line is marked on the ground parallel to the given centre line at a distance of

A. 100 cm

B. 120 cm

C. 140 cm

D. 160 cm

Answer: Option D


This Question Belongs to Civil Engineering >> Waste Water Engineering

Join The Discussion

Comments ( 3 )

  1. Dilip Joshi
    Dilip Joshi :
    3 years ago

    In the first method a line parallel to the sewer centre line is marked on the ground. This line is known as offset line and it is usually marked at a distance of 2 to 3 m or half the trench width +0.6 m from the centre line of the sewer. Along the offset line pegs are driven at an interval of 7.5 to 15 m.

  2. Gaurav Gawande
    Gaurav Gawande :
    3 years ago

    thank you anju

  3. Anju Antony
    Anju Antony :
    4 years ago

    Offset=b/2 + O. 6