If 17 labourers can dig a ditch 26 m long in 18 days, working 8 hours a day; how many more labourers should be engaged to dig a similar ditch 39 m long in 6 days, each labourer working 9 hours a day ?

A. 34

B. 51

C. 68

D. 85

Answer: Option B

Solution(By Examveda Team)

Let the total number of men to be engaged be $$x$$
More length, More labourers (Direct proportion)
Less days, More labourers (Indirect proportion)
\[\left. \begin{gathered} \,\,\,\,\,\,\,\,\,\,\,\,{\text{Lentgh 26}}:39 \hfill \\ \,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,{\text{Days 6}}:18 \hfill \\ {\text{Hours per day }}9:8 \hfill \\ \end{gathered} \right\}::17:x\]
$$\eqalign{ & \therefore {\text{ }}26 \times 6 \times 9 \times x = 39 \times 18 \times 8 \times 17 \cr & \Leftrightarrow x = \frac{{\left( {39 \times 18 \times 8 \times 17} \right)}}{{\left( {26 \times 6 \times 9} \right)}} \cr & \Leftrightarrow x = 68 \cr} $$
∴ Number of more labourers = (68 -17) = 51

This Question Belongs to Arithmetic Ability >> Chain Rule