If actual cost is $356000 and flexible budget cost is $255000, then flexible budget variance will be
A. $104,000
B. $103,000
C. $101,000
D. $102,000
Answer: Option C
Solution (By Examveda Team)
Flexible budget variance = Actual cost - Flexible budget cost= $356000 - $255000 = $101,000.