If an actual result in static budget is $2500 and corresponding budgeted amount is $2200, then static budget variance will be

A. $3,000

B. $300

C. $4,700

D. $4,500

Answer: Option B

Solution(By Examveda Team)

Static budget variance = Static budget - Corresponding budgeted amount
= $2500 - $2200 = $300.

This Question Belongs to Management >> Management Accounting