Examveda
Examveda

If an actual result is $5500 and corresponding amount of flexible budget on basis of actual level of output is $3500, then flexible budget variance will be

A. $2,500

B. $5,500

C. $3,500

D. $2,000

Answer: Option D

Solution(By Examveda Team)

Flexible budget variance = Actual result - Flexible budget
= $5500 - $3500 = $2,000.