If budgeted annual indirect cost is $60000, budgeted annual quantity of cost allocation base is $3600, then budgeted indirect cost rate will be

A. 15.67 per piece

B. 16.67 per piece

C. 14.67 per piece

D. 13.67 per piece

Answer: Option B

Solution(By Examveda Team)

Budgeted indirect cost rate = Budgeted annual indirect cost ÷ Budgeted annual quantity of cost allocation
= $60000 ÷ $3600 = 16.67 per piece

This Question Belongs to Commerce >> Costing