If budgeted direct labour hours are 4550 and direct labour cost rate is $600 per labour hour then, total direct labour cost would be
A. $4,730,000
B. $3,730,000
C. $2,730,000
D. $1,730,000
Answer: Option C
Solution(By Examveda Team)
Total direct labour cost = Budgeted direct labour hours × Direct labour cost rate= 4550 × $600 = $2,730,000