If budgeted indirect cost arte is $225 and budgeted cost allocation base is $750 per hour, then annual indirect cost (budgeted) would be
A. $168,750
B. $148,570
C. $186,750
D. $125,680
Answer: Option A
Solution (By Examveda Team)
Annual indirect cost (budgeted) = Budgeted indirect cost × Budgeted cost allocation= $225 × $750 = $168,750