If budgeted total direct labour hours are 3800 and budgeted direct labour cost is $480000, then budgeted direct labour cost rate will be
A. $126.32 per labour hour
B. $128.32 per labour hour
C. $130 per labour hour
D. $132 per labour hour
Answer: Option A
Solution (By Examveda Team)
Budgeted direct labour cost rate = Budgeted direct labour cost ÷ Budgeted total direct labour hours= $480000 ÷ 3800 = $126.32 per labour hour