If budgeted total direct labour hours are 5500 and budgeted direct labour cost is $755000, then budgeted direct labour cost rate is

A. $138 per labour hour

B. $137.27 per hour

C. $140 per labour hour

D. $142 per labour hour

Answer: Option B

Solution(By Examveda Team)

Budgeted direct labour cost = Budgeted direct labour cost ÷ Budgeted total direct labour hours
= $755000 ÷ 5500 = $137.27 per hour