If direct material cost is $5500 and prime cost is $25000, then direct manufacturing labour would be
A. $19,500
B. $30,500
C. $45,500
D. $22,500
Answer: Option A
Solution (By Examveda Team)
Direct manufacturing labour = Prime cost - Direct material cost= $25000 - $5500 = $19,500